Energy: the FerX decree on incentives and mature renewable energy sources comes into force today – what’s changing?
The measure applies to photovoltaic, wind and hydroelectric power stations, as well as facilities for treating waste gas from wastewater treatment processes
The FerX decree formally comes into force today. The text of the decree, signed by Minister Gilberto Pichetto Fratin, has been published on the website of the Ministry of the Environment and Energy Security following approval by the Court of Auditors. On 8 June, the European Commission decided not to raise any objections to the measure, deeming it compatible with the internal market. The final FerX decree contains numerous new provisions, ranging from a maximum quota of 37.15 GW of new renewable capacity to the criteria for accessing financial support.
Scope of application
The decree aims to support electricity generation from renewable energy sources with generation costs close to market competitiveness ‘by establishing a support mechanism that promotes their effectiveness, efficiency and sustainability’, taking into account the 2030 decarbonisation targets.
Photovoltaic, wind and hydroelectric power plants, as well as plants treating waste gas from wastewater treatment processes, will be eligible for the FerX support scheme. The decree also allows plants located in other EU countries or in third countries bordering Italia – with which the EU has free trade agreements – to receive aid, provided they physically export their output to Italia.
The decree remains in force until 31 December 2030 and, for plants with a capacity of 1 MW or less, for up to sixty days from the date on which a total capacity of 10 GW is reached, if this is achieved before the end of 2030.
Direct access to support
Plants with a capacity of 1 MW or less that have commenced construction following the entry into force of the decree, and which meet the performance and environmental protection requirements necessary to comply with the ‘Do no significant harm’ (DNSH) – a principle designed to reconcile economic growth with the protection of the ecosystem, ensuring that investments are carried out without compromising environmental resources – and which comply with the requirements of the relevant technical regulations on quality and safety.