Offshore wind, operators prepare for Fer 2 auctions
Waiting for March. Among the critical points: tenders also open to those who do not have all the necessary authorisations and tariffs that are too low
4' min read
4' min read
Offshore wind, while waiting for the Ministry of the Environment to announce the southern ports that will be involved in the development of dedicated shipbuilding - eyes are on Taranto, Augusta Brindisi, and Civitavecchia -, operators are preparing to take part in the March Fer 2 auctions, which offers incentives for 3.8 GW of capacity for this technology. Among the critical points: the tender is open to those who do not yet have all the necessary clearances, with the risk of financing projects that will not see the light of day, and tariffs that are too low.
Renexia's Med Wind Park
.Riccardo Toto, director of Renexia, the Toto Group company that is developing Med Wind, a 2.7 GW, 9.5 billion investment offshore park 80 km off Mazara del Vallo, the largest project in the Mediterranean, explains: "The Fer decree stipulates the need to participate in the offshore wind auction only with the Via (Environmental Impact Assessment, ndr) and not with the Autorizzazione unica (Au), issued at the end of a procedure carried out within the Conferenza dei servizi (services conference) in which all the administrations concerned participate. Statistically, only 60% of those who have the Via also obtain the Au.
This is a problem: there is a risk that the quota put out to tender will be saturated, but then only partly used, only for projects that will reach the end of the authorisation process. With the funds blocked for 60 months, which is the time needed to deliver the plant. For the onshore wind part, on the other hand, it is necessary to have both Via and Au in order to participate'.
Not to mention the costs: 'For Med Wind of Via charges we paid 5 million euro. Another 5 will be needed to start the process for the Au. How come it costs so much? However, we are moving forward and expect to complete the park process by June-July 2025,' Toto concludes.
There are two interesting ports that the company is examining for operations linked to Med Wind: Augusta and Punta Cugno (next to Augusta): 'If these infrastructures will also have funds from Mase, fine, otherwise we already have what we need in our investments,' Toto observes. While on the site where the production hub announced with MingYang will be built, he confirms the evaluation of areas in Brindisi, Taranto, and Ortona (Chieti): 'We will decide by January.