The regulatory framework

A boost for projects with two traffic lights

The process takes a maximum of ten months, with a few exceptions

 Funtap - stock.adobe.com

3' min read

Translated by AI
Versione italiana

3' min read

Translated by AI
Versione italiana

Ten months, with a further three months permitted only in exceptional circumstances: this is the maximum duration of the single procedure introduced by Article 8 of the Energy Bills Decree (Decree-Law 21/2026, converted by Law 49/2026) for the construction, expansion and operation of data centres and their associated user connection networks. The permit is issued by the competent authority for the Integrated Environmental Authorisation (AIA): the Region, or the body delegated by it, for installed thermal power between 50 and 300 MWt; the Ministry of the Environment and Energy Security for power exceeding 300 MWt. The calculation, however, is not a mere technicality. Lombardy has recently clarified that all generator sets on the site must be added together, including standby units, regardless of actual usage, simply counting their installation and presence within the infrastructure. This results in a potentially incongruous outcome: a large campus with generators totalling less than 50 MWt could fall outside the scope of the single procedure, whilst still being subject to an Environmental Impact Assessment (EIA) for other aspects, whereas a smaller centre with numerous standby generators would fall within its scope. The EIA deadlines have also been halved, but with one condition: if the screening concludes that an EIA is required, the application must be submitted within a strict 90-day deadline; failure to do so will result in the implicit withdrawal of the single application and the closure of the proceedings.

On paper, therefore, the single procedure offers operators – both Italian and international – the certainty regarding the authorisation deadlines for construction and commissioning that they have long been seeking. As for the start of the ten-month period, this does not begin from the date the application is submitted, but from the date of the notification in which the administration certifies that it is complete (as also confirmed by the MASE’s operational guidelines of 21 July 2026). For this verification, however, the ministerial guidelines do not set a deadline, deferring the timing of the individual stages to subsequent instructions. The result is a three-tiered framework: the State sets the procedure and timelines, the Region issues the licence (the Ministry for projects of 300 MWt and above), and the local authority oversees planning.

Loading...

And it is precisely town planning, together with infrastructure works, that brings together the two ‘traffic lights’ which the single procedure does not cover. The first ‘traffic light’ is town planning. Compliance with municipal plans must be documented in the application itself and, according to Mase’s guidelines, constitutes a ‘necessary and preliminary’ prerequisite for the commencement of the procedure, to be verified during the preliminary investigation. These same Mase guidelines have dispelled a widespread doubt amongst operators and interpreters: the single authorisation ‘does not in itself constitute a variation to the urban planning instruments in force’. If the site is not compatible, a planning amendment is therefore required, with its own timeframe: the technical and legal assessment of the site’s planning compatibility, prior to the investment, thus becomes crucial to the success of the operation (except in cases where a special procedure for strategic investments applies).

The second hurdle consists, at least in part, of network infrastructure. The single authorisation covers customer connections, including cable ducts, but not the infrastructure that Terna or the local distributor classify as network infrastructure. The real bottleneck, however, is the sheer volume of connection requests that the grid would have to handle – a demand that is largely virtual.

Ultimately, the ‘Bollette’ decree provided an initial response to operators who were calling for a single point of contact and a definite deadline for carrying out their investments. However, legislative work remains ongoing: the draft enabling bill on data centres (A.S. 1821), approved by the Chamber of Deputies on 24 February 2026 and now before the Senate, aims to address unresolved issues by providing for streamlined procedures with maximum time limits, the designation of projects as being in the public interest, their intended use for production purposes, priority for brownfield sites and access to the grid, and uniform rules on emissions from generator sets. One fundamental question remains: once the enabling legislation is implemented, how will national legislation be coordinated with the Lombardy law and with any laws that other regions might pass in the meantime? The risk is that the rules will multiply faster than the construction sites.

Head of FSI Real Estate Investment, Deloitte Legal