The Council of Ministers

Renewables, green light for simplifications: three tracks to speed up procedures, but operators critical

Green light for the Testo Unico that reduces the administrative regimes for the development of green sources to three. But industry associations protest: still too many barriers to building new plants or upgrading existing ones

by Celestina Dominelli

4' min read

4' min read

Green light from the Council of Ministers to the single text for the simplification of administrative procedures for green energy plants, storage systems and related works. The measure, preliminarily approved, is the result of the agreement between three ministries (Environment, Public Administration and Reforms) and responds to the objectives also set out in the NRP. Compared to the hitherto very jagged mosaic, the single text reduces the tracks for the development of green sources to three: free activity, simplified enabling procedure (PAS) and single authorisation. But the operators, starting with the most representative associations such as Elettricità Futura, did not fail to express perplexity even as the measure was being finalised, because it would introduce stakes in some cases in which no further authorisations were needed until now.

Three schemes for the development of green sources

.

But let's see in detail what the new measure provides for. The first track introduced is that of free activity, which applies, for example, to all solar plants under 10 megawatts, without any particular modification of the structure on which they are installed or occupation of land to that of the roof on which they are built, but also to the modification of existing plants (read upgrading or refurbishment). For this type of intervention, no consent deeds or declarations are required except in the case of landscape constraints. And it is on this last point that the criticism of renewable energy operators has been very much focused.

Loading...
Rinnovabili, Pichetto: ok a decreto, riduciamo molto tempi procedure

The exceptions to free activity

.

In fact, the measure introduces some exceptions, first of all when the new installation or remodelling of an existing project is on protected property or in protected natural areas: in this case, the Pas regime applies. If, on the other hand, this type of installation or remodelling relates to assets such as villas or parks that are not protected but are of uncommon beauty, or complexes of things that have a particular aesthetic value (including historical centres and nuclei), a longer procedure is triggered with the intervention of the superintendence, which must express a binding opinion (and which, if negative, blocks the process) and with the request subject to the OK of the authority protecting the landscape constraint, with a lengthening of the time required to request more in-depth preliminary investigations.

Future Electricity Surveys

.

A deadline, the latter, which can be up to 45 days and on which, as mentioned, Elettricità Futura expressed its opposition with reference to already installed plants because it 'introduces unnecessary costs and bureaucratic red tape' as it envisages a new authorisation for these projects as well. Other limitations concern the possibility of applying the mechanism of 'silence assent' (in the presence of one or more constraints on this front, the approval of the authority in charge of protecting it is required) also for projects related to renewable plants.

Simplified Authorisation Procedure (PAS)

.

The second regime, on the other hand, concerns projects that do not require permitting procedures and are not subject to environmental assessments. The measure envisages different cases depending on whether the application does not present any obstacles or is, instead, subject to municipal and/or other administrations' constraints. In the absence of prescriptions, the permit is deemed to have been issued within 30 days (which increases to 45 days if more than one act of consent is required, or to 75 if the services conference is convened).

The third track: the single authorisation

.

The last track is that of the single authorisation, which is divided into two paths depending on whether the application is submitted to the Region (for photovoltaic plants of a power equal to or greater than 1 megawatt and up to 300 megawatts, but also for wind power installations of a power equal to or greater than 60 kW or up to 300 MW, just to cite a few examples) or to the Ministry of the Environment (for all green plants above 300 MW but also for offshore installations). On this front, the duration ranges from 175 days for projects not subject to environmental assessments to 420 days in the longest case.

Pichetto: unitary and strategic framework for sector decisive for the country's future

On the measure, following the go-ahead given by the Cdm, the titular ministries that worked on fine-tuning the text spoke. "A unitary and harmonious framework," commented the Minister for the Environment and Energy Security, Gilberto Pichetto Fratin, "and strategic in a sector like renewables, which is decisive for the country's future. Today we are laying the foundations for a systemic reform, oriented towards the Pniec objectives with pragmatism and without undermining environmental protection. This measure clarifies the general framework, simplifies it where possible, and, compared to the past, stimulates private initiative in the best way: with clear rules and transparency in the timing'.

Gava: Let's speed up the deployment of renewable plants

"We simplify authorisation processes to speed up the deployment of renewable plants and storage systems. With the three authorisation regimes (free activity, PEA and single authorisation) we reduce procedures that have been stalled for too long and speed up the achievement of decarbonisation targets. Parliament, also by hearing the operators in the sector, will be able to further improve the text for a real change of pace," said Mase deputy minister Vannia Gava.

Zangrillo: first significant step to reduce the bureaucratic burden on companies

"This is a first significant step, which will have to be followed by others, to reduce the bureaucratic burden on companies operating in the renewable energy sector, simplifying and standardising procedures, with time and cost savings for the administrations involved as well," emphasised the head of the Public Administration, Paolo Zangrillo. "This is a significant step in the complex and heterogeneous panorama of administrative simplifications, which brings us closer to the goal of 200 simplified procedures, a step envisaged for this year by the National Recovery and Resilience Plan.

Casellati: important step towards the sustainability of the Italian economy

"Today we have taken an important step towards the sustainability of the Italian economy and in support of companies that want to invest in renewables and clean energy. Italy has equipped itself with a new system of incentives for productive realities, a milestone perfectly in line with the great operation of regulatory cleansing, simplification of procedures and bureaucratisation that this government has launched to make life easier for businesses and citizens. The green economy must not be a burden but an opportunity for companies. This is the way to be protagonists of the great revolution that protects our health and the environment,' said the Minister for Institutional Reforms, Maria Elisabetta Alberti Casellati.

Copyright reserved ©
Loading...

Brand connect

Loading...

Newsletter

Notizie e approfondimenti sugli avvenimenti politici, economici e finanziari.

Iscriviti