Renewables: new incentives on the way – from auctions to grants, how they work and how to access them
On 22 October, the window for submitting expressions of interest for the first competitive procedure dedicated to projects exceeding 1 megawatt will open. Direct access is provided for projects up to and including 1 MW.
Key points
- The call for expressions of interest opens on 22 October
- How to take part in auctions
- How much funding can the project receive?
- How much power is expected for the first auction
- What are the starting prices
- How is the contribution paid?
- How to access the system for installations up to 1 MW
- The weighting of location coefficients
The new incentives for renewable energy sources, managed by the GSE, are officially up and running. From 22 October, operators will be able to express their interest in participating in the first auctions linked to the final Fer X decree, which governs the support scheme for electricity generation from renewable technologies whose costs are close to market rates and which remains in force until 31 December 2030. Eligible installations include photovoltaic, wind and hydroelectric plants, as well as those utilising gas recovered from wastewater treatment processes. New installations are eligible, as are, depending on the rules for each technology, projects to refurbish existing installations or increase their capacity.
The call for expressions of interest opens on 22 October
On 6 October, the company led by Vinicio Mosè Vigilante published the calls for expressions of interest for the first competitive procedure under the final Fer X scheme. The application window will be open from 12 noon on 22 October until 12 noon on 6 November 2026. The calls for expressions of interest cover photovoltaic, wind and hydroelectric power. For photovoltaic and wind power, Nzia procedures are also envisaged, under the European Net Zero Industry Act, with additional requirements relating to security and the diversification of component supplies.
How to take part in auctions
Auctions are scheduled for projects with a capacity exceeding 1 MW, calculated in accordance with the rules set out in the decree. To take part in the competitive procedures, applicants must first submit an application to the GSE for preliminary qualification, which serves to verify that the project meets the requirements. Once the application has been submitted, an expression of interest may be submitted, even if the qualification assessment is still ongoing. For the first procedure, qualification must be obtained by 30 November 2026.
To proceed to the next stage of the financial bidding process, it is also necessary for the expression of interest to be deemed eligible. Along with the expression of interest, a provisional guarantee and documents demonstrating the operator’s financial soundness must also be submitted via the Centralised Guarantees Portal “GIGA”. At the auction, the operator proposes a reduction on the base price set for the tender: in other words, they indicate the price at which they are willing to generate the energy supported by the mechanism.
How much funding can the project receive?
The amounts of power eligible for the subsidy are referred to as quotas. In total, 27.15 GW is to be allocated through auctions, with a further 10 GW set aside for direct access by plants with a capacity of up to 1 MW. These are the quotas allocated for the various technologies: photovoltaic 10 GW, wind power 16.50 GW, hydroelectric 0.63 GW and gas from wastewater treatment processes 0.02 GW.