The no to the resolution

Ponte Stretto, what were the first findings of the Court of Auditors

Perplexities, requests for technical and procedural clarifications: In 6 pages, the Court of Auditors had already expressed doubts about the resolution with which the CIPESS gave the green light to the Strait Bridge project

by Rome Editorial Staff

PONTE SULLO STRETTO DI MESSINA RENDERING PROGETTO PROGETTI CORTE DEI CONTI BOCCIA IL PONTE SULLO STRETTO - FOTO ARCHIVIO

2' min read

Translated by AI
Versione italiana

2' min read

Translated by AI
Versione italiana

Perplexities, requests for technical and procedural clarifications. In six dense pages, the Court of Auditors had already expressed doubts on the resolution, under its examination, with which the CIPESS had given the green light to the Strait Bridge project. In the document, which had been sent to the Presidency of the Council, the investigating magistrate Valeria Franchi had reconstructed the timing of the various steps between the administrations and had asked for procedural and technical clarifications, expressing many "perplexities": these are the knots that then led to the 29 October decision, referred to the Court's collegiate body. The final findings, not yet known, will however be indicated in the motivations of the accounting magistrates, which will be known in 30 days.

September surveys

La Corte già a settembre sottolineava “la necessità di acquisire chiarimenti ed elementi informativi” sulla delibera: “risulterebbe non compiutamente assolto l’onere di motivazione - scriveva - difettando, a sostegno delle determinazioni assunte dal Cipess, anche in relazione a snodi cruciali dell’iter procedimentale, una puntuale valutazione degli esiti istruttori”. Nel primo esame della Corte dei Conti, veniva indicato che la delibera del Cipess “si appalesa più come una ricognizione delle attività intestate ai diversi attori istituzionali del procedimento che come una ponderazione delle risultanze di dette attività, sotto il profilo sia fattuale sia giuridico”. Non convinceva la Corte neanche la procedura per trasmetterle gli atti (gli ormai famosi link che erano stati inviati) e inoltre: “Si chiedono chiarimenti anche con riferimento alla tempistica osservata per la trasmissione del provvedimento Mit-Mef con cui è stato assentito il terzo atto aggiuntivo”. “Parimenti - si legge

Loading...

Business Plan Charges

On the charges in the economic plan, the Court pressed: 'Moreover, perplexities arise with regard to the misalignment between the amount sworn by the company Kpmg on 25 July 2025 - quantified at EUR 10,481,500,000 - and the amount of EUR 10,508,820,773 certified in the economic framework approved on 6 August 2025.

Technical aspects

Dito puntato anche su aspetti tecnici: “Quanto alle stime di traffico - al piano tariffario di cui allo studio redatto dalla TPlan Consulting - poste a fondamento del Pef si chiedono chiarimenti in ordine alle valutazioni svolte da codesto Comitato in merito alle modalità di scelta della predetta società di consulenza e agli esiti di detto studio anche in relazione agli approfondimenti istruttori svolti in occasione della riunione preparatoria del Cipess”. Tra gli aspetti procedurali si metteva in evidenza anche che “in via generale, con riferimento alla fase progettuale, si osserva che non risulta in atti il parere del Consiglio Superiore dei lavori pubblici (voto 220 del 1997). Codesto Comitato vorrà integrare la documentazione in conformità non essendo reperibile sul sito istituzionale”. Per la parte economica si chiedevano, fra l’altro, “chiarimenti in merito ai costi della sicurezza e all’incremento registrato nel 2011 (euro 206.521.286) rispetto a quanto attestato nel progetto prelimin