The Milan–Bologna high-speed line reopens after eight days of works
Six 200-tonne switches have been replaced. Speed restrictions will remain in place until 28 August, whilst there are still 1,300 construction sites operating daily across the network and major service disruptions to Genoa and Rome
At 4.55 am on Tuesday 18 August, the Frecciarossa 9505 from Milan to Naples was the first train to resume services on the high-speed line between Milan and Bologna. Rete Ferroviaria Italiana (RFI) has reopened the entire route following the suspension from 10 to 17 August, during which trains ran between Piacenza and Milan on the standard line. Full speed will not be restored immediately but will be gradually reintroduced, increasing until full service is resumed on 28 August.
Six trades of 200 tonnes
RFI carried out work simultaneously at three sites: two at the Livraga marshalling yard, in the Lodi area, and one at the Piacenza Ovest junction. More than a hundred engineers replaced six sets of points (the mechanisms that allow trains to change tracks), each 140 metres long and weighing 200 tonnes.
Whilst the works were underway, high-speed trains bypassed the closed section by using the conventional line. Around 200 high-speed trains, capable of reaching speeds of 300 kilometres per hour, travel on the Milan–Bologna route every day, but RFI concentrated the works during the week of Ferragosto due to the ‘significant drop in passenger numbers on the route’.
The Ferragosto works and the network upgrade
This is nothing new for the Milan–Bologna line. This is the third consecutive Ferragosto with similar works taking place on the line: in 2024, three construction sites between Castelfranco Emilia and Fidenza had replaced other points; in 2025, services on the line were suspended again for a week at Parma, Campegine and Rubiera.
In 2026, the entire Italian rail network will have an average of 1,300 active construction sites every day, comprising new works, maintenance and technological upgrades. In 2025, RFI invested €11.6 billion, 49 per cent more than in 2023. Thirty-seven per cent went towards network maintenance and resilience, with the remainder allocated to major infrastructure projects.

