Energy and high-tech

Data centres in Italy: demand for the Terna network is booming (+48 per cent)

In the first eight months of the year alone, there was a surge of over 48 per cent: the lion’s share of applications came from Lombardy, Lazio and Piedmont

 Stock.adobe.com

4' min read

Translated by AI
Versione italiana

4' min read

Translated by AI
Versione italiana

The rapid growth of data centres continues to drive demand for electricity, at least on paper. According to figures recorded by Terna, requests to connect new data centre projects to the electricity grid reached 95.38 gigawatts (data recorded on 21 August). This is a significant jump when compared to 2021, when requests of this kind stood at 1 gigawatt.

Since then, a veritable race has been underway, which first saw the number of applications rise to 5.40 GW in 2023, before climbing to 31.28 GW the following year: a boom which, as documented by the group led by Pasqualino Monti, is concentrated mainly in northern Italia and, in particular, in Lombardy, which alone has received 290 applications totalling 46 GW – largely centred on Milan – followed by Lazio, Piedmont and Apulia.

Loading...

The peak in the Centre-North

Of the 531 applications received by Terna to date – 300 of which have been received since the start of January alone (58.7 GW, which is 48.2 per cent more than in the first eight months of 2025, when the total stood at 215 (39.6 GW)) – only 15 (1.88 GW) have reached the most advanced stage of development, a sign that the bulk of the applications represent potential demand that will not materialise. Nevertheless, the figures remain highly significant. In August alone, according to Terna, there were 8 new applications for 0.87 GW (3 applications from Lombardy, 2 from Puglia, and 1 application each from Emilia-Romagna, Sicily and Veneto), whilst 6 applications lapsed, representing a capacity of approximately 1.3 GW. In July, by contrast, 17 applications were received for a total capacity of 1.68 GW: over the two months, 7 applications came from Lombardy (857 MW), 4 from Piedmont (350 MW), 2 from Campania (200 MW), 2 from Basilicata (200 MW) and, finally, 10 applications from Emilia-Romagna, Puglia, Lazio, Sicily, Veneto and Friuli-Venezia Giulia, totalling 1.1 GW. As in August, however, eight applications lapsed or were withdrawn.

A profile of the proposers

Applications come mainly from engineering firms and developers of this type of plant or of renewable energy plants, but also from special-purpose vehicles and property firms. Whilst it is clearly not possible to obtain a detailed overview of the activities of the applicant, one important point can be noted: during the authorisation process, end-users step in to take ownership of the applications from the development and design firms, in much the same way as occurs in the renewable energy sector.

Returning to the more than 530 applications submitted since the start of the year, only around 10 per cent can be directly attributed to data centre operators or investment funds dedicated to them, whilst the remaining 90 per cent is divided between around 30 per cent attributable to design, development and special-purpose companies, and 60 per cent comprising a diverse group of larger property and logistics firms and private operators.

Terna’s role

This concludes the updated overview of applications for connection to the electricity grid, which must be submitted to Terna, specifying the required power and the location of the installation, as well as the documents required under current regulations. As soon as the application is received, the electricity network operator issues a general minimum technical solution (STMG), which includes the connection solution and the connection fees to be paid upon signing the connection contract.

Acceptance of the quotation must be carried out by the applicant and, should the STMg require new works on the national transmission grid for the connection, a number of steps will be triggered: 1) the proposer’s request for a financial quotation for the design of the RTN works; 2) the preparation of the financial offer, setting out the timescales and costs for the design, issued by Terna; 3) acceptance of the financial offer and payment of the fee by the proposer; 4) the design and initiation of the authorisation process (which also includes the inter-departmental consultation provided for under the new regime introduced by the ‘Dl Bollette’) for the data centre and the consumer network works, to be carried out by the applicant with the competent authority (the bodies of the Ministerial or Regional AIA); and, finally, the design and initiation of the authorisation process for any Rtn works required for connection, to be carried out by Terna at Mase.

Once the authorisation procedures have been completed, the so-called ‘detailed minimum technical solution (STMD), in which Terna sets out in detail the works and costs required to connect the data centre to the grid, and the actual connection contract is drawn up, following which the works will be carried out and the facility brought into operation.

Data centres already connected

To date, eight data centres are connected to the grid as specific consumption units: the first has been connected since 2017, whilst three of them came into service in 2026. A further four connections are expected in the coming months: these applications are all concentrated in Lombardy. The total number of connected data centres is, of course, higher: at present, the figure stands at 226 facilities with a combined capacity of 513 MW, but the majority of these are smaller and connected to the distribution network or to complex industrial plants. As for the increase in final consumption resulting from the expected growth of data centres, this is already factored into Terna’s scenarios, which estimate, under the most challenging assumptions, an increase of up to 17 per cent.